Cannabis Program Update & EIR Timeline
             
        
Timeline (subject to change)
Updated 9/25/2025
June 8, 2021 Board approval of initial resources request (June 8, 2021 Board Summary Report)
- 
Public Visioning and Idea Generating – July 2021 through September 2021- 
Week of August 2 – Begin scheduling with stakeholders for small group outreach
- 
Week of August 9 – Topic-based Public Visioning Sessions
- 
Week of August 16 – Conduct small group outreach, sessions to be recorded and posted online
- 
Week of August 23 – Conduct small group outreach, sessions to be recorded and posted online
- 
Week of August 30 – Conduct a County-wide digital survey to request additional information
- 
Week of September 13 – Board of Supervisors package posted online and made available to the public
- 
September 28, 2021 – Board Workshop on Project Goals (September 28, 2021 Board Summary Report)
 
- 
- 
Development of Draft Ordinance Framework – October 2021 through March 15, 2022- 
Complete a draft ordinance framework including all potential program elements to consider in the Environmental Impact Report (EIR) for the new program
- 
March 15, 2022 - Board of Supervisors adopted Cannabis Program Update Framework
 
- 
- 
Development and Refinement of Draft Ordinance – March 2022 through October 2022- May 20, 2022 - Initiate Competitive Request for Proposal (RFP) Process for an EIR Consultant
- 
Continue public outreach to develop and refine potential program elements, listen to concerns, and develop options to address concerns
- 
October 2022 – Preliminary draft ordinance, and any general plan amendments needed for consistency, complete for environmental analysis
 
- 
Environmental Impact Report (EIR) – October 2022 through April 2025- 
October 4, 2022 - Board of Supervisors approval of EIR Professional Services Agreement (October 4, 2022 Item Materials)
- 
February 6, 2023 – Notice of Preparation published for the Draft EIR to kick off the EIR scoping effort
- 
March 8, 2023 at 6:00PM – Virtual public scoping meeting
- 
Seek public input on what Potential Environmental Impacts should be considered in the EIR
- December 13, 2023 - Public Informational Meeting to provide an update on the development of "residential enclave" mapping and key program elements
- 
April 2024 - Legislative draft ordinance, draft General Plan Amendment, and revised sensitive use setback viewer published for 30 day public review
- July 2024 - Revised legislative draft ordinance, draft General Plan Amendment, pipeline provisions, and responses to frequently asked questions published
- 
Conduct environmental analysis of the proposed draft ordinance
- 
Provide public access to technical studies used in the environmental analysis, as available
- 
Provide regular public status updates throughout the EIR process
- 
April 15, 2025 - Board of Supervisors informational update (April 15, 2025 Item Materials)
 
- 
- 
Draft Ordinance and EIR Approval – May 2025 through ~October 2025 - WE ARE HERE- May 16, 2025 – Draft EIR published for 60-day public review
- 
June 19, 2025 – First Planning Commission Hearing (June 19, 2025 Planning Commission Information)
- 
August 7, 2025 – Additional Planning Commission Hearing (August 7, 2025 Planning Commission Information)
- September 3, 2025 – Final EIR published, including responses to comments
- 
September 17 & 18, 2025 – Final Planning Commission Hearings (Link to September 17, 2025 Planning Commission Information / Link to September 18, 2025 Planning Commission Information)
- 
October 28, 2025 – Board of Supervisors Hearing on Proposed Ordinance and EIR
 
 Translate