Auditor-Controller Treasurer-Tax Collector Department
EFS PeopleSoft Annual Catch-up Event Milestone Update
Published: November 28, 2017
The EFS Support Organization has adjusted the Annual Catch-up Event (ACE) milestones as a result of the wildfires. We are currently in the process of completing our Systems Integration Testing (SIT), and will begin User Acceptance Testing (UAT) on January 8th, 2018. Although our milestones were pushed back roughly one month, we still expect to complete the Annual Catch-up Event in the first quarter of 2018.
Here are the updated Annual Catch-up Event milestones:
- Production Change Freeze 12/29/2017 until Go-Live
- User Acceptance Testing Estimated to start on 01/08/2018
- Training One month prior to Go-Live date
- Go-Live End of 1st Quarter 2018
The EFS Support Organization continues to work diligently on meeting our Annual Catch-up Event milestones while also offering support to the EFS end-user community. We will continue to routinely provide updates on the Annual Catch-up Event milestones.